Public Institution Mandatory Installation Program
A program requiring public institutions to source a minimum percentage
of the energy needed for newly built, expanded, or remodeled buildings with a total floor area of 1,000 ㎡ or more from renewable energy
Mandatory Installation Ratio by Year
The mandatory installation ratio is being raised year by year, and by 2030 public buildings will be required to source 40% of their energy needs from renewable energy.
|
‘ 20 ~ ’21
|
‘ 22 ~ ’23
|
‘ 24 ~ ’25
|
‘ 26 ~ ’27
|
‘ 28 ~ ’29
|
‘ 30 ~
|
|
30%
|
32%
|
34%
|
36%
|
38%
|
40%
|
Adjustment Coefficient
|
New & Renewable Energy Source
|
Annual Recognized Energy Production per 1kW Installed
|
|
Category
|
Type
|
Unit Production
|
Correction Factor
|
Total Unit Production (kWh/kW-year)
|
|
Solar
|
PV (Building-Attached)
|
1,358
|
0.95
|
1,290
|
|
BIPV (Building-Integrated)
|
923
|
6.12
|
5,649
|